Exam technique and practice

Exam technique

  • When drawing a network, use activity on arc, arrows on every arc, dashed dummies, and one start and one finish event. Check each activity against the precedence table at the end.
  • Write early and late times in the boxes provided at each event. Examiners check the largest-value rule at merges and the smallest-value rule at bursts.
  • Give the critical path as a list of activities, and the project length with units.
  • For float, show the calculation: late end −- duration −- early start.
  • In scheduling questions, state the lower bound calculation, then give a full schedule: who does what, and when.

Common mistakes

  • Taking the smallest value in the forward pass, or the largest in the backward pass. Fix: forward is largest, backward is smallest.
  • Using a dummy where none is needed, or missing one that is. Fix: check every activity's preceding activities against the table.
  • Calling an activity critical just because its events have equal early and late times. Fix: its float must be 0.
  • Forgetting dummies when finding float or event times. A dummy is an activity of duration 0: include it in both passes.
  • Rounding the lower bound for workers down. Fix: always round up.
  • Scheduling an activity before all its preceding activities have finished.

Check yourself

  1. Activity G runs from event 4 (early 9, late 11) to event 6 (early 17, late 17) and lasts 5 days. Find its total float.
  2. Two activities end at event 5, with early start times 3 and 6 and durations 8 and 4. Find the early time of event 5.
  3. Two activities start at event 3, with durations 5 and 2, ending at events with late times 15 and 11. Find the late time of event 3.
  4. Activities in a project last 4, 6, 3, 8, 5, 7 and 2 days, and the critical path is 16 days. Find a lower bound for the number of workers.
  5. An activity with total float 3 is delayed by 5 days. What is the effect on the project?
  6. Activity J has earliest start 6, duration 4 and float 2. Must it be in progress at time 8.5?
  7. Why might a project need more workers than the lower bound?
Show answers
  1. 17−5−9=317 - 5 - 9 = 3 days
  2. max⁡(11,10)=11\max(11, 10) = 11
  3. min⁡(10,9)=9\min(10, 9) = 9
  4. 3516=2.19\frac{35}{16} = 2.19, so 3
  5. The project is delayed by 2 days
  6. Latest start is 8 and earliest finish is 10, so yes
  7. Precedences may force workers to wait for activities to finish, so not all the available working time can be used