Topic 4 · Lesson 2 of 4

Event times, critical paths and float

The example project

The worked examples in this lesson and the next use the activity network below. The number in brackets after each activity is its duration in days.

A(4)B(6)C(3)D(6)E(2)F(4)12345

The forward pass: early event times

The early event time of an event is the earliest time at which all the activities leading into it can be finished. Work forwards from the start, where the early time is 0. For each event, add each incoming activity's duration to the early time at its start, and take the largest.

The backward pass: late event times

The late event time of an event is the latest time at which it can happen without delaying the whole project. Work backwards from the finish, where the late time equals the early time (the project length). For each event, subtract each outgoing activity's duration from the late time at its end, and take the smallest.

Critical activities and float

An activity from event ii to event jj, with duration dd, has

total float=late time of j−d−early time of i\text{total float} = \text{late time of } j - d - \text{early time of } i

The total float is how long the activity can be delayed, or extended, without delaying the project. A critical activity has total float 0. The critical activities form one or more critical paths from start to finish, and the length of a critical path is the minimum time for the project. Any delay to a critical activity delays the whole project by the same amount; a delay to a non-critical activity delays the project only by the amount it exceeds the float.

On a critical activity, the early time at its start equals the late time there, and the same at its end, and the duration is exactly the difference. Equal early and late times at both ends are necessary but not enough: check the duration too.

Worked example

Event times

The network above has activities A(4), B(6), C(3), D(6), E(2) and F(4), with durations in days.

Show solution
  1. Forward pass: event 1: 0; event 2: 4; event 3: max⁡(0+6,4+3)=7\max(0 + 6, 4 + 3) = 7; event 4: max⁡(4+6,7+2)=10\max(4 + 6, 7 + 2) = 10; event 5: 10+4=1410 + 4 = 14.
  2. Backward pass: event 5: 14; event 4: 10; event 3: 10−2=810 - 2 = 8; event 2: min⁡(8−3,10−6)=4\min(8 - 3, 10 - 6) = 4; event 1: min⁡(4−4,8−6)=0\min(4 - 4, 8 - 6) = 0.
  3. Floats: A: 4−4−0=04 - 4 - 0 = 0; B: 8−6−0=28 - 6 - 0 = 2; C: 8−3−4=18 - 3 - 4 = 1; D: 10−6−4=010 - 6 - 4 = 0; E: 10−2−7=110 - 2 - 7 = 1; F: 14−4−10=014 - 4 - 10 = 0.
  4. The critical path is A D F, and the project takes 14 days.

Try it: build the network from a precedence table and run the forward and backward passes yourself, event by event, then see the floats, the cascade chart and a schedule for any number of workers.

Try it: simulation

Critical path analysis

Loading the simulation…

Practise this topic

Both are part of Premium.