Cascade charts, resources and scheduling

Cascade (Gantt) charts

A cascade chart draws each activity as a bar against a time scale. Critical activities go in a row at the top (shaded above). Each other activity is drawn on its own row, starting at its earliest start time, with its total float shown as a dashed box after it. The chart below is for the worked example.

02468101214ADFBCETime (days)

The chart answers questions quickly:

  • An activity must be happening at time tt if its latest start time is at or before tt and its earliest finish time is after tt. At time 5.5 in the example, D must be happening (it is critical), and so must B (latest start 2, earliest finish 6) and C (latest start 5, earliest finish 7). At time 7.5 only D must be happening: E may start as late as 8.
  • The latest start time of an activity is its earliest start plus its float.

Resource histograms

If each activity needs a known number of workers, a resource histogram shows the total number of workers needed at each moment, usually with every activity starting as early as possible. It is a step graph: time across, workers up. Activities with float can be moved, within their float, to level the histogram: to reduce the peak number of workers without delaying the project.

To decide whether a peak can be reduced, look at which activities must be happening at that time (critical activities, and others that cannot be moved away from it). If those alone need more workers than are available, the project must be delayed.

Lower bound for the number of workers

If each activity needs one worker, then

lower bound=sum of all activity durationscritical path length, rounded up\text{lower bound} = \frac{\text{sum of all activity durations}}{\text{critical path length}}, \text{ rounded up}

In the example, 4+6+3+6+2+414=2514=1.79\frac{4 + 6 + 3 + 6 + 2 + 4}{14} = \frac{25}{14} = 1.79, so at least 2 workers. The bound may not be achievable: precedences can force workers to wait.

Scheduling

To schedule activities to workers:

  1. A worker who is free is given an activity whose preceding activities have all finished.
  2. If there is a choice, give the activity with the smallest latest finish time (the one that must be finished soonest).
  3. If no activity is available, the worker waits until one is.

Show the schedule as a chart, one row per worker, with the activities and their start and finish times.

Worked example

Is the lower bound enough?

In the example, can 2 workers finish in 14 days? A and D are critical, so one worker must do A from 0 to 4 and D from 4 to 10, then F from 10 to 14. The other worker must do B, C and E. B must finish by 8 (the late time of event 3), so it must start by 2; it lasts 6 days, so it occupies that worker until at least 6. C cannot start before 4, so it runs from 6 at the earliest, finishing at 9, and E then finishes at 11, after its latest finish time of 10. So 2 workers need at least 15 days. With 3 workers, C can run from 4 to 7 and E from 7 to 9, and the project is finished in 14 days.