Critical path analysis

A big project, such as building a house, staging a festival or launching an app, is made of many activities, some of which cannot start until others have finished. Critical path analysis turns these dependencies into a network and answers the questions a project manager cares about: how quickly can the whole project be done, which activities must not slip, how much slack do the others have, and how many workers are needed?

What you need to know

  • Model a project with an activity network, using activity on arc, from a precedence (dependency) table.
  • Use dummies correctly, both to show dependence and to make each activity uniquely defined by its events.
  • Find early and late event times with a forward and a backward pass.
  • Identify critical activities and the critical path; find the total float of an activity.
  • Draw and interpret cascade (Gantt) charts.
  • Draw and interpret resource histograms, and adjust start times within float to reduce the number of workers needed.
  • Find a lower bound for the number of workers, and schedule activities to workers.

Key points

  • Activity on arc: activities are arcs, events are nodes; dummies (zero duration) show dependence and keep activities uniquely defined.
  • Forward pass: early times, take the largest. Backward pass: late times, take the smallest.
  • Total float = late time at end − duration − early time at start; critical activities have zero float.
  • Cascade charts show each activity at its earliest start with its float; an activity must be in progress at tt if its latest start is at or before tt and its earliest finish is after tt.
  • Lower bound for workers = total duration ÷ critical path length, rounded up; schedule by giving a free worker the available activity with the smallest latest finish time.