Activity networks and dummies

Activity on arc

In an activity network, each activity is an arc (an arrow), and each event is a node, drawn as a circle. An event is the moment when all the activities leading into it have finished; the activities leading out of it can then start. The project has one start event and one finish event.

A precedence table lists each activity with its immediately preceding activities: the ones that must be finished just before it can start. You only need the immediate ones: if C depends on B and B depends on A, write "B" for C, not "A, B".

To draw a network from a precedence table:

  1. Start with the activities that have no preceding activities; they all leave the start event.
  2. For each other activity, its start event must be reached by exactly its preceding activities.
  3. Join all the final activities to a single finish event.
  4. Check every activity against the table, and number the events so that every arrow goes from a smaller number to a larger one.

Dummies

A dummy is an activity of zero duration, drawn as a dashed arrow. It is used for two reasons.

  • Dependence: when two activities share some, but not all, of their preceding activities. For example, if C depends on A only and D depends on A and B, then C starts at the end of A, B ends at its own event, and a dummy from the end of A to the end of B lets D depend on both without making C depend on B.
  • Uniqueness: every activity must be uniquely defined by its start and end events, so no two activities may join the same pair of events. If P and Q both follow K and both precede R, draw Q to its own end event and add a dummy from there to the end of P.

Use as few dummies as possible: if a question says "using the minimum number of dummies", each dummy must have a reason.